South Flores construction frustrates businesses as SAWS works to finish sewer project
Changing closures and reduced parking have disrupted customer access and neighborhood travel. SAWS says work on seven manholes remains.

Changing closures, detours and limited parking along South Flores Street are making it harder for customers to reach local businesses as San Antonio Water System works to finish a $10 million sewer project. The work has also complicated residents’ trips through the neighborhood, including school drop-offs.
At Karolina’s Antiques, employee Samantha Lozano said customers call daily to ask whether the store is open and how to get there. Some give up when they cannot find a way in. The disruption has hit during a busy stretch for the shop, which sells antiques and hosts a weekly community market.
Lozano estimates the work has cost the business at least a couple thousand dollars over the last few months. She said reduced foot traffic has also made vendors hesitant to join the market. For neighborhood businesses that depend on in-person visits, unpredictable access and parking can mean lost sales even when a shop remains open.
How the work is affecting the area
Construction crews have used a nearby parking area for equipment and loading, leaving customers to park farther away and walk to the store. Lozano said barricades and access change from day to day, making it difficult to tell customers what route to take or when the disruption will end.
Resident Lamis Pimento said rerouted traffic has made it harder to get in and out of the neighborhood and to drop off her children at school. Another resident, Sandra Avila, criticized what she described as inconsistent activity at the site.
What SAWS says about the timeline
SAWS said the sewer line replacement is complete, but crews still need to close seven manholes. The utility attributed delays to recent weather and conflicts with existing fiber-optic infrastructure. It said crews encountered underground cable structures that could not be moved, temporarily pausing work while options were evaluated.
SAWS said a solution has been identified and work on the manholes is expected to resume next week. The utility expects the project to finish in the next several weeks and said it remains on track for completion by the end of the year. It has not provided a more specific completion date in the information it shared.
This report draws on information from KSAT.